Supplying, connecting, controlling and monitoring devices for the whole plough complex in LW Bogdanka
backDate:
IV 2014Country:
PolandThis contract included delivery of transformer stations with the voltage ratio 6/3,3kV, contactor switches, communication and interlocks system with sensors. Control and monitoring system was created including remote parameterization of protections. The control system was configured so that the control is possible from both ploughed wall and from mine head.